EVC: Small Capital Repairs Sub-project: Parking Lot Remediation (Phase 2 design)

Budget: $2,903,449

Designer: CSW/ST2

Description: Remediation of damaged and poor asphalt paved parking and drive areas.

Phase 2: Contract construction work is complete. All parking lots are open for Fall 2018. Certain change order work will continue into October 2018.