San Jose Evergreen Community College District
Citizens' Bond Oversight Committee
2016-2017 Annual Report
Measure G-10 Project List
As of June 30, 2017
Project NameBudgetExpended
Vehicular Circulation Entrances$1,300,990$28,261
Demolition of Jaguar Gym Locker Rooms, Auxiliary Structures and Site Improvements$1,001,218$49,009
Group II Equipment - $200,000/year for 10 years $2,541,917$1,142,323
Restroom Fixtures & Plumbing Upgrades$500,000$0
ADA Transition Plan: Accessibility Survey & Improvements$554,561$2,400
CTE Improvements$401,525$48,073
IT Infrastructure Improvements $5,683,871$3,218,613
Technology Upgrades $3,173,711$2,388,769
New Maintenance and Operations Building$8,504,960$245,730
Theater Accessibility and Entrance Improvements $1,728,105$265,270
Parking Lot and Street Repairs$203,727$65,880
Access Control$796,675$342,870
Utilities PH III$2,468,827$274,177
Wayfinding, Signage and Site Fencing$1,218,532$297,228
Audio Visual Systems Improvements$758,499$207,040
Central Plant Equipment & Controls$1,506,454$143,618
Physical Security PH II$2,626,079$311,619
New Gym Sitework and Auxiliary Buildings$14,886,432$6,617,012
Small Capital Repairs$10,832,378$5,575,162
Relocate Adaptive PE$301,224$43,673
Roofing Repairs$1,024,169$590,391
San Jose-Evergreen Community College Extension$1,607,818$830,843
Building Interior Finishes$299,911$299,141
GE Building Interior Finishes$1,825,873$1,810,058
Career Technical Education (CTE): Renovation of 100/200 buildings$11,686,160$11,686,160
Repurpose Boiler Plant$589,305$589,305
Utility Extensions and Emergency Generator$5,718,806$5,718,806
Campus Site Improvements$1,137,429$1,137,429
Photo Lab Relocation$750,984$750,984
Iron Workers Training Center$1,540,891$1,540,891
GE HVAC Upgrade and Campus HVAC Controls Extension$936,952$936,952
Parking Lot and Walkway Improvements$640,874$640,874
Campus Water System mapping and consolidation$396,145$396,145
Physical Security$646,381$646,381
(Consolidated) 100-200-Boiler Plant Demo and New Parking Lot$0$0
(Consolidated) Exterior Lighting Phase II$0$0
(Consolidated) Vocational Technology Bldg$0$0
(Consolidated) Landscaping$0$0
(Consolidated) Irrigation$0$0
(Consolidated) Hardscape$0$0
(Consolidated) Wayfinding$0$0
(Consolidated) Energy Efficiency- Photovoltaic$0$0
(Consolidated) Campus Generator Project$0$0
(Consolidated) Site Fencing & Marquee Signage$0$0
(Cancelled) Renovate Building K$0$0
(Cancelled) Renovate- General Education Building$0$0
(Deferred) Theater Demo and New Parking Lot$0$0
(Deferred) Exterior Lighting Upgrades & Repairs$0$0
Campus Contingency - San Jose City$2,567,347$0
Total San Jose City College:$92,358,733 $48,841,087
Project NameBudgetExpended
EVC Vehicles$98,766$91,872
Group II Equipment - 200,000/year for 10 years$1,947,211$692,699
Technology Upgrades $1,103,719 $736,254
Admin and Student Services Remodel and Consolidation$183,621$153,733
Physical Security $655,754$637,431
Roble Demolition - Acacia Alterations$5,720,171$2,201,162
Campus Site Improvements$4,187,379$3,667,041
Signage and Wayfinding$1,658,662$1,434,198
Small Capital Repairs$14,894,259$10,689,444
IT Infrastructure Improvements$11,264,941$8,214,861
South Campus Development$47,067,274$45,599,660
Automotive Technology$17,807,688$17,745,588
Central Green$3,031,223$3,022,340
Parking Lot and Street Repairs $1,300,199$1,155,278
Relocate EVC's Telephone MPOE to Central Utility Building$602,937$69,339
Central Plant and Police Renovation$15,001,807$15,001,807
Utilities Projects and Upgrades$961,997$961,997
Energy Efficiency - Photovoltaic $10,841,425$10,841,425
Campus Water Service Replacement Project$814,505$814,505
(Consolidated) GED4$0$0
(Consolidated) Hardscape- Circulation and Plazas$0$0
(Consolidated) Landscaping$0$0
(Consolidated) Irrigation$0$0
(Consolidated) Exterior Lighting Upgrade Phase II$0$0
(Consolidated) Vehicular Circulation$0$0
(Cancelled) New Campus Police Building$0$0
(Cancelled) Engineering and Applied Technology$74,520$74,520
(Deferred) Repurpose Gullo II$0$0
Campus Contingency - Evergreen$4,120,219$0
Total Evergreen Valley College: $143,338,276$123,805,152
Project NameBudgetExpended
Vehicle Replacement$1,308,123$1,272,847
Enterprise Resource Planning Conversion $5,036,395$4,800,532
ADA Transition Plan Assessment$500,000$84,007
Energy Efficiency - Clean Energy, Year 2$395,947$294,506
Police Safety Communication Upgrade $400,000$108,024
Infrastructure Upgrade $4,991,495$3,376,146
New District Services Building$13,080,293$12,756,749
MDF Relocation$2,401,692 $1,841,029
Controls Extension Project (Energy Conservation)$320,253$243,111
(Consolidated) Group II Equipment - Includes safety and security $0$0
District-Wide Contingency$354,128$0
Management and Related Costs (3% of const hard costs) $1,336,284$375,031
Election/Legal/EIR/DO Labor and Related (3% of const hard costs)$3,642,616$296,754
Total District:$33,767,226$25,448,737
Unallocated Interest Earnings $519,547 $0
Program Contingency$2,329,860 $0