San Jose Evergreen Community College District
Citizens' Bond Oversight Committee
2020-2021 Annual Report
Measure G-10 Project List
As of June 30, 2021
| Project Name | Budget | Expended |
|---|---|---|
| Group II Equipment | $6,400,359 | $5,283,550 |
| Campus Lighting Upgrades | $57,335 | $18,700 |
| Child Development Center- Phase I | $4,201,147 | $51,468 |
| Student Center Improvements | $3,361,910 | $139,668 |
| Jaguar Multicultural Center | $16,584,730 | $117,546 |
| SJCC CEQA Compliance Consulting Services | $457,543 | $375,972 |
| Central Plant Boilers | $1,000,000 | $0 |
| SJCC Vehicles | $102,670 | $28,657 |
| Small Capital Repairs - Facilities Upgrades - SJCC | $5,468,543 | $0 |
| IT Infrastructure Improvements | $5,727,356 | $4,185,463 |
| Technology Upgrades | $5,367,938 | $4,433,236 |
| IT and Tech Equipment - SJCC | $5,468,543 | $0 |
| Career Education Complex | $188,482,987 | $8,180,036 |
| ADA Improvements | $501,749 | $14,368 |
| Stadium Renovation | $7,950,423 | $404,540 |
| Central Plant Rehabilitation | $20,027,403 | $640,500 |
| SJCC Elevator Modernization | $3,623,111 | $123,765 |
| Access Control, Intrusion Alarms, and Monitoring Systems | $6,044,214 | $753,941 |
| New Maintenance and Operations Building and Emergency Operations Center | $22,204,311 | $11,633,777 |
| Theater Improvements | $9,130,126 | $4,261,074 |
| Science Building Mechanical Upgrade | $2,251,235 | $817,728 |
| Entrance Door Replacement | $457,496 | $338,125 |
| Student Services Resource and Drop-in Center | $1,556,432 | $1,008,189 |
| Small Capital Repairs | $7,953,949 | $5,908,665 |
| Demolition and Site Preparations for New CTE | $3,113,894 | $2,491,002 |
| New Swing Space Project | $2,070,361 | $1,339,029 |
| Storm Water Management Remediation | $958,542 | $946,257 |
| Library Interior Upgrades | $1,235,112 | $1,199,848 |
| Campus-wide Painting- SJCC | $1,556,375 | $1,556,334 |
| Telecomm/Utility Master Plan | $411,455 | $275,409 |
| Softball Field Renovation | $1,139,809 | $1,055,853 |
| Campus HVAC Phase II | $137,934 | $122,844 |
| San Jose Evergreen Community College Extension - Irrigation | $1,034,196 | $1,029,501 |
| Restroom Fixtures & Plumbing Upgrades | $4,484,988 | $3,542,100 |
| AV Improvements Phase II | $270,970 | $211,806 |
| Career Technical Education (CTE): Renovation of 100/200 buildings | $11,666,035 | $11,666,035 |
| Repurpose Boiler Plant | $589,305 | $589,305 |
| Utility Extensions and Emergency Generator | $5,718,806 | $5,718,806 |
| Campus Site Improvements | $1,137,429 | $1,137,429 |
| Photo Lab Relocation | $750,984 | $750,984 |
| New Gym Sitework and Auxiliary Buildings | $14,198,448 | $14,198,448 |
| Iron Workers Training Center | $1,540,891 | $1,540,891 |
| GE HVAC Upgrade and Campus HVAC Controls Extension | $936,952 | $936,952 |
| Parking Lot and Walkway Improvements | $640,874 | $640,874 |
| San Jose-Evergreen Community College Extension | $1,557,757 | $1,557,757 |
| Admissions and Records | $54,115 | $54,115 |
| Site Utility and Topography | $268,930 | $268,930 |
| Campus Water System mapping and consolidation | $396,145 | $396,145 |
| Physical Security | $646,381 | $646,381 |
| Parking Lot and Street Repairs - Phase II | $1,077,716 | $1,077,716 |
| Parking Lot and Street Repairs | $260,221 | $260,221 |
| Access Control | $922,128 | $922,128 |
| Relocate Adaptive PE | $510,299 | $510,299 |
| Roofing Repairs | $908,700 | $908,700 |
| Utilities PH III | $312,268 | $312,268 |
| Wayfinding, Signage and Site Fencing | $2,038,064 | $2,038,064 |
| ADA Transition Plan: Accessibility Survey & Improvements | $1,526 | $1,526 |
| Audio Visual Systems Improvements | $445,515 | $445,515 |
| Building Interior Finishes | $299,420 | $299,420 |
| Campus HVAC Equipment & Controls | $990,195 | $990,195 |
| CTE Improvements | $68,911 | $68,911 |
| GE Building Interior Finishes | $1,811,737 | $1,811,737 |
| Physical Security PH II | $2,931,081 | $2,931,081 |
| Interior Finishes Upgrades | $103,441 | $103,441 |
| (Consolidated) 100-200-Boiler Plant Demo and New Parking Lot | $0 | $0 |
| (Consolidated) Exterior Lighting Phase II | $0 | $0 |
| (Consolidated) Vocational Technology Bldg | $0 | $0 |
| (Consolidated) Landscaping | $0 | $0 |
| (Consolidated) Irrigation | $0 | $0 |
| (Consolidated) Hardscape | $0 | $0 |
| (Consolidated) Wayfinding | $0 | $0 |
| (Consolidated) Energy Efficiency- Photovoltaic | $0 | $0 |
| (Consolidated) Campus Generator Project | $0 | $0 |
| (Consolidated) Site Fencing & Marquee Signage | $0 | $0 |
| (Cancelled) Renovate Building K | $0 | $0 |
| (Cancelled) Renovate- General Education Building | $0 | $0 |
| (Deferred) Vehicular Circulation Entrances | $29,227 | $29,227 |
| (Deferred) Theater Demo and New Parking Lot | $0 | $0 |
| (Deferred) Kingman Intersection Off-Site and On-Site Improvements | $0 | $0 |
| (Deferred) Exterior Lighting Upgrades & Repairs | $0 | $0 |
| Campus Contingency - San Jose City | $21,434,046 | $0 |
| SJCC - Future Projects | $8,956,241 | $0 |
| Total San Jose City College: | $411,954,260 | $115,333,760 |
| Project Name | Budget | Expended |
|---|---|---|
| EVC Vehicles | $200,572 | $200,572 |
| ADA Improvements | $218,156 | $19,466 |
| Admissions and Records Remodel to Emergency Ops. Center | $3,750,003 | $75 |
| EVC CEQA Compliance Consulting Services | $392,282 | $292,477 |
| Campus-wide Furniture, Fixtures, and Equipment | $300,000 | $0 |
| Small Capital Repairs - Facilities Upgrades - EVC | $5,468,541 | $0 |
| Group II Equipment | $1,664,852 | $1,454,902 |
| IT Infrastructure Improvements | $10,991,995 | $8,241,966 |
| Technology Upgrades | $2,354,295 | $2,206,027 |
| IT and Tech Equipment - EVC | $5,468,541 | $0 |
| Student Services Center | $88,218,683 | $4,677,795 |
| Language Arts Building | $45,047,927 | $3,498,178 |
| Sequoia Upgrades / Nursing Addition | $31,221,509 | $794,182 |
| General Education Building | $43,061,224 | $1,913,387 |
| Student Activities Center | $26,100,001 | $159,343 |
| Mathematics, Sciences, Social Sciences Canopy | $790,047 | $9,865 |
| Entry Road and New Parking Lot 4/5 | $11,668,000 | $619,883 |
| Physical Education and Sports Complex | $6,957,509 | $4,676,212 |
| Cedro Renovation and West Campus ADA Upgrades | $10,317,762 | $8,381,689 |
| Campus Way Finding / Ground Lighting | $3,338,094 | $1,543,974 |
| North Fire Lane / ADA | $8,141,882 | $3,077,554 |
| Campus-wide Building Signage | $725,838 | $567,313 |
| Small Capital Repairs | $16,812,081 | $16,239,772 |
| Physical Education Accessibility Improvements | $2,702,331 | $2,702,331 |
| EVC: Campus Painting Project | $4,002,759 | $3,801,185 |
| MS3 Exterior Stair Lighting | $162,556 | $162,344 |
| Campus Environmental Control | $612,864 | $612,834 |
| Gullo II Multipurpose Remodel | $2,478,355 | $2,365,428 |
| Security Hardware | $482,764 | $468,175 |
| South Campus Development | $45,703,845 | $45,703,845 |
| Admin and Student Services Remodel and Consolidation | $153,733 | $153,733 |
| Roble Demolition - Acacia Alterations | $6,699,838 | $6,699,838 |
| Automotive Technology | $17,745,588 | $17,745,588 |
| Campus Site Improvements | $4,201,371 | $4,201,371 |
| Central Green | $3,022,340 | $3,022,340 |
| Signage and Wayfinding | $1,616,483 | $1,616,483 |
| San Felipe Digital Message Sign | $842,465 | $842,465 |
| Acacia Renovation Phase III | $1,324,452 | $1,324,452 |
| Gullo Student Space Repurpose and Renovation | $2,080,270 | $2,080,270 |
| Montgomery Hall Interior Updating | $336,380 | $336,380 |
| PE ADA Improvements - Pathways / Fieldhouse | $2,215,580 | $2,215,580 |
| Gullo 2nd Floor - Student Services Center Renovation | $2,962,161 | $2,962,161 |
| Central Plant and Police Renovation | $15,001,807 | $15,001,807 |
| Utilities Projects and Upgrades | $961,997 | $961,997 |
| Energy Efficiency - Photovoltaic | $10,841,425 | $10,841,425 |
| Campus Water Service Replacement Project | $814,505 | $814,505 |
| Parking Lot and Street Repairs | $1,155,278 | $1,155,278 |
| Physical Security | $637,431 | $637,431 |
| Parking Lot Remediation- Phase II | $3,344,063 | $3,344,063 |
| Pavement Preservation / Roadway and Curb Marking | $60,999 | $60,999 |
| EVC Utility Updating and Mapping | $152,584 | $152,584 |
| Relocate EVC's Telephone MPOE to Central Utility Building | $172,809 | $172,809 |
| (Consolidated) GED4 | $0 | $0 |
| (Consolidated) Hardscape- Circulation and Plazas | $0 | $0 |
| (Consolidated) Landscaping | $0 | $0 |
| (Consolidated) Irrigation | $0 | $0 |
| (Consolidated) West Campus ADA Upgrades | $0 | $0 |
| (Consolidated) Cesar Chavez Grove | $0 | $0 |
| (Consolidated) Exterior Lighting Upgrade Phase II | $0 | $0 |
| (Consolidated) Vehicular Circulation | $0 | $0 |
| (Cancelled) New Campus Police Building | $0 | $0 |
| (Cancelled) Engineering and Applied Technology | $74,520 | $74,520 |
| (Cancelled) Campus-wide Storm Water Pollution Prevention Plan | $0 | $0 |
| (Deferred) Repurpose Gullo II | $0 | $0 |
| Campus Contingency - Evergreen | $14,006,836 | $0 |
| EVC - Future Projects | $0 | $0 |
| Total Evergreen Valley College: | $469,780,184 | $190,808,852 |
| Project Name | Budget | Expended |
|---|---|---|
| District Services Furniture & Equipment | $989,897 | $606,345 |
| Vehicle Replacement | $1,879,220 | $1,577,879 |
| District-wide Elevator Assessment | $755,032 | $85,928 |
| Ground Lease Debt Relief (15+ years) | $8,200,400 | $1,285,543 |
| Technology and Security | $61,582,074 | $4,563,401 |
| District Services Printing & Digital Imaging | $757,987 | $574,429 |
| District Services Computer Replacement | $494,447 | $488,176 |
| District Services Network Storage/Servers | $750,000 | $0 |
| District Services Network Monitoring Appliances | $50,000 | $0 |
| District-wide Security - Key System Upgrades | $579,300 | $181,075 |
| Data Center Acquisition & Implementation | $1,500,000 | $507,470 |
| New District Services Building | $16,101,868 | $13,418,737 |
| District Office Elevators Safety and Accessibility Upgrades | $1,906,931 | $1,463,637 |
| District-wide Building Management System | $1,122,222 | $589,316 |
| ADA Transition Plan Assessment | $665,042 | $202,513 |
| Security Systems Assessment & Design Consulting Services | $272,852 | $248,319 |
| Energy Efficiency - Clean Energy | $511,340 | $511,340 |
| Demolition of San Felipe District Office and South Bay Academy | $1,846,625 | $1,846,625 |
| MDF Relocation | $1,923,380 | $1,923,380 |
| Controls Extension Project (Energy Conservation) | $318,022 | $318,022 |
| Police Safety Communication Upgrade | $623,139 | $623,139 |
| Enterprise Resource Planning Conversion | $4,800,532 | $4,800,532 |
| Infrastructure Upgrade | $3,819,982 | $3,819,982 |
| (Consolidated) Group II Equipment - Includes safety and security | $0 | $0 |
| (Cancelled)Telecommunications Consolidation Antennas | $0 | $0 |
| District and District-wide Contingency | $9,791,017 | $0 |
| Management and Related Costs | $4,648,528 | $311,552 |
| Election/Legal/EIR/DO Labor and Related | $8,437,573 | $1,980,256 |
| Total District/District-wide (campus) Budget: | $134,327,409 | $41,927,595 |
| Unallocated Interest Earnings | $1,811,845 | $0 |
| Program Contingency | $11,600,000 | $0 |