San Jose Evergreen Community College District
Citizens' Bond Oversight Committee
2019-2020 Annual Report
Measure G-10 Project List
As of June 30, 2020
Project NameBudgetExpended
Group II Equipment$6,316,573$4,896,526
Career Education Complex$142,407,980$843,750
Property Acquisition $10,000,000$27,398
Technology Building Renovation$2,172,044$0
Campus Lighting Upgrades$55,000$16,365
Telecomm/Utility Master Plan$387,663$89,456
Child Development Center- Phase I $4,195,020$43,601
Student Center Improvements $6,076,000$107,216
Jaguar Multicultural Center$16,573,380$89,700
Track & Field Renovation $1,937,835$15,440
Central Plant Renovation$40,000,000$131,624
Cosmetology, Esthetics, & Reprographics$2,201,216$0
SJCC CEQA Compliance Consulting Services$615,176$1,868
SJCC Vehicles$102,670$28,657
Access Control, Intrusion Alarms, and Monitoring Systems$6,004,015$202,670
Small Capital Repairs - Facilities Upgrades - SJCC$5,468,543$0
IT Infrastructure Improvements$5,727,356$4,185,463
Technology Upgrades$5,308,313$4,243,532
IT and Tech Equipment - SJCC$5,468,543$0
Theater Improvements$8,906,948$1,379,348
Student Services Resource and Drop-in Center$823,121$177,893
Demolition and Site Preparations for New CTE$3,540,391$1,946,966
New Maintenance and Operations Building and Emergency Operations Center$21,730,537$2,330,491
ADA Improvements$500,000$12,619
Entrance Door Replacement$423,500$211,877
Softball Field Renovation$1,500,000$468,655
Small Capital Repairs$9,945,807$5,900,523
Restroom Fixtures & Plumbing Upgrades$8,451,182$447,846
Interior Finishes Upgrades$130,026$103,441
New Gym Sitework and Auxiliary Buildings$14,264,189$14,168,403
San Jose-Evergreen Community College Extension$1,553,153$1,527,146
New Swing Space Project$2,007,540$1,276,208
Storm Water Management Remediation$918,708$885,487
Science Building Mechanical Upgrade$1,819,463$506,409
Library Interior Upgrades$1,310,224$1,083,262
Campus-wide Painting- SJCC$1,366,565$1,366,223
Admissions and Records$47,357$47,357
Site Utility and Topography$350,000$235,887
Campus HVAC Phase II$302,976$75,263
San Jose Evergreen Community College Extension - Irrigation$1,028,250$1,023,555
Parking Lot and Street Repairs - Phase II$1,077,408$1,077,408
Access Control$916,975$916,975
Relocate Adaptive PE$522,618$473,601
Wayfinding, Signage and Site Fencing$2,038,064$2,038,064
Audio Visual Systems Improvements$445,496$445,496
Campus HVAC Equipment & Controls$1,010,960$990,195
CTE Improvements$403,262$66,547
Physical Security PH II$2,931,081$2,931,081
AV Improvements Phase II$341,372$207,208
Career Technical Education (CTE): Renovation of 100/200 buildings$11,666,035$11,666,035
Repurpose Boiler Plant$589,305$589,305
Utility Extensions and Emergency Generator$5,718,806$5,718,806
Campus Site Improvements$1,137,429$1,137,429
Photo Lab Relocation$750,984$750,984
Iron Workers Training Center$1,540,891$1,540,891
GE HVAC Upgrade and Campus HVAC Controls Extension$936,952$936,952
Parking Lot and Walkway Improvements$640,874$640,874
Campus Water System mapping and consolidation$396,145$396,145
Physical Security$646,381$646,381
Parking Lot and Street Repairs$260,221$260,221
Roofing Repairs$908,700$908,700
Utilities PH III$312,268$312,268
ADA Transition Plan: Accessibility Survey & Improvements$1,526$1,526
Building Interior Finishes$299,420$299,420
GE Building Interior Finishes$1,811,737$1,811,737
(Consolidated) 100-200-Boiler Plant Demo and New Parking Lot$0$0
(Consolidated) Exterior Lighting Phase II$0$0
(Consolidated) Vocational Technology Bldg$0$0
(Consolidated) Landscaping$0$0
(Consolidated) Irrigation$0$0
(Consolidated) Hardscape$0$0
(Consolidated) Wayfinding$0$0
(Consolidated) Energy Efficiency- Photovoltaic$0$0
(Consolidated) Campus Generator Project$0$0
(Consolidated) Site Fencing & Marquee Signage$0$0
(Cancelled) Renovate Building K$0$0
(Cancelled) Renovate- General Education Building$0$0
(Deferred) Vehicular Circulation Entrances$29,227$29,227
(Deferred) Theater Demo and New Parking Lot$0$0
(Deferred) Kingman Intersection Off-Site and On-Site Improvements$0$0
(Deferred) Exterior Lighting Upgrades & Repairs$0$0
Campus Contingency - San Jose City$21,434,046$0
SJCC - Future Projects$8,956,241$0
Total San Jose City College:$409,661,688 $86,891,600
Project NameBudgetExpended
EVC Vehicles$201,434$200,572
ADA Improvements$250,000$17,671
Sequoia Upgrades / Nursing Addition $31,199,999 $41,708
Admissions and Records Remodel to Emergency Ops. Center$3,750,001$0
General Education Building $43,000,001$48,266
Student Activities Center$34,100,000$67,149
Campus-wide Building Signage$490,000$47,674
EVC CEQA Compliance Consulting Services$384,610$1,462
Small Capital Repairs - Facilities Upgrades - EVC$5,468,541$0
Group II Equipment$1,648,803$1,112,842
IT Infrastructure Improvements$10,991,995$8,241,966
Technology Upgrades$2,353,938$2,205,671
IT and Tech Equipment - EVC$5,468,541$0
Student Services Center $97,269,999$1,093,415
Language Arts Building$39,615,390$314,085
Kinesiology and Physical Education $5,200,000$451,559
Cedro Renovation and West Campus ADA Upgrades$9,881,000$1,863,063
North Fire Lane / ADA $7,315,999$456,125
Physical Education Accessibility Improvements$2,545,820$2,442,662
PE ADA Improvements - Pathways / Fieldhouse $2,092,777$2,045,381
EVC: Campus Painting Project$4,332,212$1,824,684
Gullo II Multipurpose Remodel $2,487,200$596,618
Campus Way Finding / Ground Lighting$3,840,299$186,284
Security Hardware $475,000$287,579
Small Capital Repairs$16,730,893$15,872,994
Acacia Renovation Phase III $1,288,254$1,261,350
Gullo Student Space Repurpose and Renovation$2,078,752$2,078,752
Montgomery Hall Interior Updating $363,609$336,380
Gullo 2nd Floor - Student Services Center Renovation$3,048,543$2,738,492
MS3 Exterior Stair Lighting $162,556$162,344
Campus Environmental Control$565,000$542,540
Parking Lot Remediation- Phase II $3,342,211$3,341,391
Pavement Preservation / Roadway and Curb Marking$100,000$55,358
EVC Utility Updating and Mapping $228,918$150,175
South Campus Development$45,703,845$45,703,845
Admin and Student Services Remodel and Consolidation $153,733$153,733
Roble Demolition - Acacia Alterations$6,699,838$6,699,838
Automotive Technology $17,745,588$17,745,588
Central Green$3,022,340$3,022,340
Signage and Wayfinding $1,616,483$1,616,483
San Felipe Digital Message Sign$842,465$842,465
Central Plant and Police Renovation$15,001,807$15,001,807
Utilities Projects and Upgrades$961,997$961,997
Energy Efficiency - Photovoltaic $10,841,425$10,841,425
Campus Water Service Replacement Project$814,505$814,505
Parking Lot and Street Repairs $1,155,278$1,155,278
Physical Security$637,431$637,431
Relocate EVC's Telephone MPOE to Central Utility Building $172,809$172,809
(Consolidated) GED4$0$0
(Consolidated) Hardscape- Circulation and Plazas$0$0
(Consolidated) Landscaping$0$0
(Consolidated) Irrigation$0$0
(Consolidated) West Campus ADA Upgrades$0$0
(Consolidated) Cesar Chavez Grove$0$0
(Consolidated) Exterior Lighting Upgrade Phase II$0$0
(Consolidated) Vehicular Circulation$0$0
(Cancelled) New Campus Police Building$0$0
(Cancelled) Engineering and Applied Technology$74,520$74,520
(Cancelled) Campus-wide Storm Water Pollution Prevention Plan$0$0
(Deferred) Repurpose Gullo II$0$0
Campus Contingency - Evergreen$15,597,054$0
EVC - Future Projects$0$0
Total Evergreen Valley College: $467,514,783$159,731,646
Project NameBudgetExpended
District Services Furniture & Equipment$970,000$173,574
Vehicle Replacement $1,863,360$1,562,020
District-wide Elevator Assessment$747,860$56,191
Ground Lease Debt Relief (15+ years)$8,100,000$778,303
Technology and Security$67,225,000$1,904,107
District Services Printing & Digital Imaging $750,211$549,178
District Services Computer Replacement$450,000$438,507
District Services Network Storage/Servers$750,000$0
District Services Network Monitoring Appliances$50,000$0
District-wide Security - Key System Upgrades $575,000$0
District Office Elevators Safety and Accessibility Upgrades$1,200,000$146,332
Energy Efficiency - Clean Energy$501,978$501,701
New District Services Building$13,388,802$13,040,720
Demolition of San Felipe District Office and South Bay Academy $2,322,687$1,742,102
Police Safety Communication Upgrade$642,228$621,990
ADA Transition Plan Assessment$664,638$202,109
Enterprise Resource Planning Conversion$4,955,698$4,800,532
Infrastructure Upgrade $3,849,411$3,811,607
Security Systems Assessment & Design Consulting Services$250,000$225,467
MDF Relocation$1,923,380$1,923,380
Controls Extension Project (Energy Conservation)$318,022$318,022
(Consolidated) Group II Equipment - Includes safety and security$0$0
(Cancelled)Telecommunications Consolidation Antennas $0$0
District and District-wide Contingency$9,007,414$0
Management and Related Costs $5,915,289$1,823,969
Election/Legal/EIR/DO Labor and Related$8,590,297 $3,258,126
Total District/District-wide (campus) Budget:$135,011,275$32,795,842
Unallocated Interest Earnings $1,152,479 $0
Program Contingency$11,600,000 $0