San Jose Evergreen Community College District Citizens Bond Oversight Committee
Measure G-04 Project List
As of June 30, 2015
Project NameBudgetExpended
Physical Education Gymnasium$22,880,265$2,947,243
Modernization of Existing Facilites$565,653$465,965
Multi-Disciplinary Building (Humanities/Art/Math) $28,850,211$28,611,537
SJCC Campus Safety Upgrades$296,687$296,687
Science & Math Educational Complex (Science Complex) $19,189,964$19,189,964
Career Technology (Applied Sciences)$1,538,948$1,538,948
SJCC Facility Master Plan$619,597$619,597
Cosmetology/Reprographics Remodel$5,631,333$5,631,333
Site & Parking Improvements$1,999,039$1,999,039
Maintenance & Operations Renovations$219,618$219,618
Utilities Infrastructure$3,562,632$3,562,632
Voice Data Upgrades$476,443$476,443
Multi-use Athletic/Softball Field$5,643,805$5,643,805
Minor Facilities Modifications$192,672$192,672
SJCC Furniture & Equipment$199,326$199,326
San Jose City College Total: $91,866,192$71,594,809
Project NameBudgetExpended
Central Green/Arts Plaza$6,266,591$1,380,742
EVC Modernization of Existing Buildings$19,977,124$19,889,414
Classroom Complex for Visual and Performing Arts (Arts Complex) $20,717,707$20,717,707
EVC Campus Safety Upgrades$376,168$540,263
EVC Facility Master Plan$313,797$313,797
Site & Parking Improvements$5,223,397$5,223,397
Student Service Renovation$919,275$919,275
EVC Furniture & Equipment$1,565,780$1,565,780
Health/Physical Education Center$1,928,261$1,928,261
EVC Central Plant & Utilites Infrastructure Upgrades$3,538,455$3,538,455
Voice Data Upgrades$768,544$768,544
East Plaza Reconfiguration$0$0
Evergreen Valley College Totals:$61,595,100$56,621,541
Project NameBudgetExpended
Joint Use 21st Century Post-Secondary Education Center $10,028,186$1,062,992
District Office Renovation$3,045,712$3,045,712
DW Master Plan- District Standards$121,814$121,814
DW Scheduled Maintenance (Local Match)$462,544$462,544
DW Technology Upgrades$7,956,348$7,956,348
DW Sustainability Plan$1,288,469$1,288,469
General Safety Upgrades$2,153,269$2,153,269
DW Legal Fees$628,066$618,201
DW Project Admin & Other Operating Expenses $3,771,468$3,517,029
Restructure Lease Revenue$10,391,474$10,391,474
District Totals:$39,847,349$30,617,851